We build the industry’s highest performing teams by hiring the industry’s best. Dedicated to safety, operational excellence and an outstanding client experience, we work collaboratively with you to accomplish your goals.
| NO. | CONTRACT NO. | CONTRACT TITLE | PROJECT VALUE IN SR. | CLIENT |
| 1 | 6600030549 | PREPARATION OF WELLSITES & ACCESS ROADS | 275,721,773.00 SAR | SAUDI ARAMCO |
| 2 | 6600023887 | PREPARATION OF WELLSITES & ACCESS ROADS | 132,844,879.00 SAR | SAUDI ARAMCO |
| 3 | 6510664748 | UPGRADING OF HARMALIYAH ROAD | 18,139,500.00 | SAUDI ARAMCO |
| 4 | XXXXXXX | LABOR CAMP DEV. OF STAGE 2 - KHONAINI INT'L CO. LTD IN ASSOCIATION WITH M.S. AL SUBAI EST | 50,000,000.00 SAR | M. S. AL SUBAI |
| 5 | 021-101 R | LABOR CAMP DEV. OF STAGE 2 - KHONAINI INT'L CO. LTD IN ASSOCIATION WITH M.S. AL SUBAI EST | 128,871,639.10 SAR | ROYALCOMMISSIONfor JUBAIL & YANBU
|
| 6 | 66000415591 | PREPARATION OF WELLSITES & ACCESS ROADS | 194,300,250.00 SAR | SAUDI ARAMCO |
| 7 | AR7549/02/08 | CNNSTRUCTION OF EVAPORATION | 18,193,399.73 SAR | AL SUWAIDI IND. SERVICES CO. |
| 8 | 659-C05 | COMPLETING THE SITE DEVELOPMENT | 41,997,035.00 SAR | ROYAL COMMISSIONfor JUBAIL & YANBU |
| 9 | 6510277270 | RE-ASPHALTING PAVEMENT OF | 750,000.00 SAR | SAUDI ARAMCO |
| 10 | 202-C16 | Earthwork for Zone E & F | 47,662,246.00 SAR | ROYALCOMMISSIONfor JUBAIL & YANBU |
| 11 | 6400052303 | PREPARATION OF WELLSITES | 162,655,368.67 SAR | SAUDI ARAMCO |
| 12 | 6600012065 | UPGRADE WASTE WATER TREATMENT | 10,912,818.89 SAR | M.S.AL-SUWAIDI |
| 13 | 531-P42-AG | ASPHALT PAVING FOR | 612,000.00 SAR | ROYAL COMMISSION |
| 14 | 19/31/23/56/00/00/4 | ASPHALT PAVING & SIDE WALKS | 4,948,200.00 SAR SAR | JUBAIL MUNICIPALITY |
| 15 | 220045 | EXTENTION OF OUTSIDE | 4,462,553.00 SAR | JUBAIL MUNICIPALITY |
| 16 | 19/31/23/50/00/00/4 | ASPHALT PAVING & SIDE WALKS | 1,322,047.30 SAR | JUBAIL MUNICIPALITY |
| 17 | 19/31/23/54/00/00/4 | ASPHALT PAVING & SIDE WALKS | 4,931,162.00 SAR | JUBAIL MUNICIPALITYT |
| 18 | 19/31/23/52/00/00/4 | REHABILITATION & REPLACEMENT OF | 4,942,468.00 SAR | JOINT OPERATIONS KUWAIT |
| 19 | JO/HC33/MP00 | CONST. OF 5000 BBLS UNDERGROUND | KD. 97,265.500 SAR | JOINT OPERATIONS KUWAIT |
| 20 | JO/HC01/MP01 | SECURITY FENCE FOR WAFRA FIELD | KD. 356,216.000 SAR | JOINT OPERATIONS KUWAIT |
| 21 | 220153 | EXTENSION OF OUTSIDE | 1,470,000.00 | SAUDI TELECOM CO. |
| 22 | 400563/049 | EXPANSION OF RECLAMATION CHEMICAL | 668,750.00 SAR | SAUDI ARAMCO |
| 23 | 40824/03 | PREPARATION OF WELLSITES & ACCESS ROADS | 42,118,365.87 SAR | SAUDI ARAMCO |
| 24 | P.R. # 0691 | RESTORATION OF EPCCO | 5,000,000.00 SAR | EASTERN PROVINCE |
| 25 | BGP/SC-004/94 | Addl. Berri Gas Plant | 15,131,731.65 SAR | DAELIM |
| 26 | 4/74600/19/51 | Modification of Existing | 6,920,326.00 SAR | JUBAIL MUNICIPALITY |
| 27 | 37720/00 | South Plant Site Grading | 11,871,846.00 SAR | SAUDI ARAMCO |
| 28 | SC-7250-2501-A-92 | Construction of Camp Facilities with | 12,000,000.00 SAR | AL MOJIL GROUP |
| 29 | 60010/00 | Site Preparation & Installation of Crude | 24,000,000.00 SAR | SAUDI ARAMCO |
| 30 | 37258/00 | Construction of 4 Lane & Modify | 2,719,399.58 SAR | SAUDI ARAMCO |
| 31 | 37258/00 | Earthwork & Grading Incr.XI | 8,002,546.36 SAR | SAUDI ARAMCO |
| 32 | 37258/00 | ASPHALT WORK AT KHOBAR DAMMAM HIGH WAY | 3,280,185.00 SAR | AL NAFJAN |
| 33 | 37258/00 | ASPHALT WORK AT KHOBAR DAMMAM HIGH WAY | 2,893,536.00 SAR | SAUDI TOGER CO FOR TRADING |
| 34 | 37258/00 | ASPHALT WORK AT KHOBAR DAMMAM HIGH WAY | 606,373.00 SAR | EMMAR INFRASTRUCTURE FOR CON.CO LTD
|